The roof has started | Page 5 | PASOTI
  • This site is sponsored by Lang & Potter.

The roof has started

Apr 21, 2007
79
10
Is the roof going to be extended to the left to be the same length as the Mayflower terrace in phase 1?
 
Sep 24, 2003
1,160
100
Plymouth
A third A frame was being constructed in the car park earlier as I was up there. They have also been busy filling one of gaps between the installed A frames today.
 

Heathrow Green

🇰🇪 Welicar Donor
Brickfields Donor
✨Pasoti Donor✨
🌟Sparksy Mural🌟
Jul 12, 2011
972
105
An airport just outside London
I was looking at this from cam one just now.

Almost had a shock when it looked like one of the cherry pickers was collapsing only to realise that it was actually a fun-fair ride in the background.
 
Sep 24, 2003
1,160
100
Plymouth
The crane is back and it looks like they're connecting it up to the red girder, so looks like more A frames to go in this morning. Cams 1 + 2 currently down for me
 

Argylegames

Administrator
Staff member
✅ Evergreen
✨Pasoti Donor✨
🌟Sparksy Mural🌟
Jun 12, 2006
7,882
1,380
69
Hampshire, UK
www.argylegames.org.uk
arrythewurzel":10isf3ng said:
Have the contractors gone on two weeks hols - doesn't seem much happening this week?
There was a comment on GoS that whilst the roof was being lifted into place there couldn't be any work at the rear of the grandstand for safety reasons.

The crane did lift another of the horizontal beams into place along the back earlier in the week.
 

Ottawa Green

Site Admin
Staff member
🇨🇦🇨🇦🇨🇦🇨🇦🇨🇦🇨🇦
Cream First
✅ Evergreen
✨Pasoti Donor✨
Sep 18, 2003
24,184
2,293
72
Ottawa, Canada
6 roof trusses now installed, I assume one more to go.
 

Ottawa Green

Site Admin
Staff member
🇨🇦🇨🇦🇨🇦🇨🇦🇨🇦🇨🇦
Cream First
✅ Evergreen
✨Pasoti Donor✨
Sep 18, 2003
24,184
2,293
72
Ottawa, Canada
and up goes #7 truss