The Grumpy Loyal":2qmgukej said:DrewPAFC":2qmgukej said:The Grumpy Loyal":2qmgukej said:Abbotts Ann Green":2qmgukej said:So when it has been, are you going to come back here and apologise for getting it wrong?
Getting what wrong? It has been stated publicly that the contract hasn’t yet been signed? It is a statement of fact!
Again, not quite:
“We signed a contract for the enabling works but the main contract is due to be signed in the middle of June.
Again, failing to see what your issue is?
That’s where the Devil is in the detail innit. Is it just outbuildings being ripped out, or Main Grandstand?
What would be more telling would be the reasons for the main contract not being signed yet. But I’m not sure JB stretches that far in the transparency dept.
The point that I don’t understand the fuss about is that it wouldn’t matter if the contract for the main works had been signed, as works can’t start until all the other phases and preliminary works are well underway or completed, works on these are currently being done.