dunlop":18v35cnu said:IJN":18v35cnu said:So what’s currently ‘going on’ then Mike! :crazy:
Putting it mildly being economical with the truth, it’s a sham at HP.
We're going to need a bit more detail than that.
dunlop":18v35cnu said:IJN":18v35cnu said:So what’s currently ‘going on’ then Mike! :crazy:
Putting it mildly being economical with the truth, it’s a sham at HP.
dunlop":20p3qtn9 said:Putting it mildly being economical with the truth, it’s a sham at HP.
Kentishgreen":1l5yr8tm said:The step ladder is just an illusion
IJN":ffkmnp2q said:I hope you mentioned this to JB when you and Oddball chatted to him at Torquay then!
Kentishgreen":14t8wkko said:So all those photos on GOS, the club’s own photos, the webcams and the blog prove conclusively that there has been no progress at Home Park not even any old fashioned progress. JB has employed a stunning illusionist then!
dunlop":3o9jh0q8 said:Kentishgreen":3o9jh0q8 said:So all those photos on GOS, the club’s own photos, the webcams and the blog prove conclusively that there has been no progress at Home Park not even any old fashioned progress. JB has employed a stunning illusionist then!
Grandstand refurb nearly finished is it.
dunlop":q83579c7 said:Kentishgreen":q83579c7 said:So all those photos on GOS, the club’s own photos, the webcams and the blog prove conclusively that there has been no progress at Home Park not even any old fashioned progress. JB has employed a stunning illusionist then!
Grandstand refurb nearly finished is it.
tonycholwell":19pskepl said:Argy1e":19pskepl said:andyr1963":19pskepl said:Fact is because John Back says all conditions have been met, does not mean Plymouth City Council believe that all the pre conditions have been met. If they had been, we could have had an "all systems go" announcement from Argyle.
The article you've clearly not read":19pskepl said:With the important, stadium-specific ‘pre-commencement’ conditions of the project now all satisfied to an appropriate standard, it really is all systems go
Try reading it?
Personally, I have found it and the associated applications a riveting experience.
2 quick points:
1. There its no update on the PCC planning portal in respect of Condition 19. This happens sometimes but you would expect to see it documented early next week at the latest.
2. Jon, who I have known for a long time now is normally very precise with language. So, I though this was the case when he wrote "stadium-specific ‘pre-commencement’. This may or may not pertain to the fact application 17/01684/OUT was a Hybrid application, which also included the proposed ice rink and outline permission for what is being called the Western gateway.
I may have missed it, but still no news on signing up the main contractor. This clearly impinges on the new changing rooms and supporters bar, let alone the Grandstand.
Whatever the delay, be it planning or otherwise I would hope that work will proceed with some speed now so that it is ready for the start of season 2019/20.
IJN":3tyvuqj7 said:Can’t get into this end!
So is the drainage a showstopper or not?
IJN":3lycrz2z said:Can’t get into this end!
So is the drainage a showstopper or not?
Stuart House":1e7jpx6b said:IJN":1e7jpx6b said:Can’t get into this end!
So is the drainage a showstopper or not?
Much to the disappointment of some it seems it's not!
Basically says condition 19 partially discharged and works can proceed on the grandstand, with four week extension to resolve the rest.
Obviously some will pick up on the fact it is not fully resolved, but at last things can be BUILT!